Guide
General Binding Rules: a quick check
If you are responsible for a septic tank or a small sewage treatment plant in England, you are usually classed as the operator. In many cases you do not need your own environmental permit, but only if the discharge meets the General Binding Rules (GBR). The rules below apply in England. There are different rules in Scotland, Wales and Northern Ireland.
The rules differ if the treated liquid goes into the ground (a drainage field) or into surface water (a river, stream or similar). They also differ for discharges that started or changed significantly on or after 2 October 2023, and there are extra rules for discharges that started on or after 1 January 2015.
Start with the official overview: Septic tanks and sewage treatment plants: what you need to do on GOV.UK.
A practical check
- Work out where the liquid goes: into the ground, or into a watercourse. A septic tank must not discharge to a watercourse; that route needs a sewage treatment plant.
- Check the daily volume. Under the current GBR, a discharge to ground must be no more than 2 cubic metres (2,000 litres) a day, and a discharge to surface water no more than 5 cubic metres (5,000 litres) a day. GOV.UK has a daily discharge calculator for houses, and points commercial or holiday uses to British Water’s Flows and Loads guidance.
- If a public foul sewer is nearby, you may need to connect rather than keep a private discharge. This applies in particular to discharges that started on or after 1 January 2015, and to new or significantly changed discharges from 2 October 2023. The official pages explain when a connection is required.
- New or significantly changed discharges from 2 October 2023 have further rules. Do not assume an older system is automatically fine if it has been moved, enlarged, or switched from ground to surface water (or the other way around).
- The sewage should be domestic in nature (for example from toilets, bathrooms and kitchens). The discharge must not cause pollution. Tanks and plants should be installed and maintained properly, and sludge taken away by an authorised person, such as a registered waste carrier.
If you cannot meet the rules, GOV.UK says you should connect to the public foul sewer where that is reasonable, change the system so that it does meet the rules, or apply for a permit.
Official rule pages: discharges to the ground and discharges to surface water. The statutory list of General Binding Rules from 2 October 2023 is also on GOV.UK.